The project site lies due south of Marsh Island, LA in SMI Area Block 205, Gulf of Mexico. A new 12" riser was installed on Platform "A" and connected to a new 12"pipeline routed southeast approximately 2000 feet to the Equilon (Auger) 20" pipeline and connected via a subsea tie-in to an existing flange. The tie-in included a check valve and ball valve within the final spool. Another ball valve and blind flange was added on the other side of a tee connection of the tie-in for a future connection. The new pipeline transports oil collected at Platform "A" from multiple upstream sources to the Equilon 20" pipeline.

CTI's project management and engineering responsibilities included:
  • Design of the riser and pipeline
  • Permitting
  • Procurement of materials
  • Preparation of the bid packages
  • Assisting in Contract negotiations
  • Approval of Contractor's procedures
  • Overall management of the installation phase of work.